Closed
Milestone started on Feb 4, 2025

Log failover and metrics

Work by: elias, ln5.

This will include getting a metrics dashboard and such setup for jellyfish/seasalp; and this will likely be linked as an example that others can take inspiration from.

https://gitlab.torproject.org/tpo/tpa/team/-/issues/40677 might be a useful reference, good pointers from anarcat wrt. prometheus stuff.

Changes that touch core/ are reviewed by nisse.

Related to this milestone: %Monitoring 2025, phase I (i.e., what elias and ln5 is working on wrt. monitoring / metrics)

  • Work items 1
  • Merge requests 1
  • Participants 0
  • Labels 0
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Feb 4, 2025
From
Feb 4 2025
Due date
No due date (306 days elapsed)
1
Work items 1
Open: 0 Closed: 1
1
Merge requests 1
Open: 0 Closed: 0 Merged: 1
0
Releases
None
Reference: sigsum%"Log failover and metrics"